Completed
What the client
asked for.
A fifteen-year-old villa requiring a complete internal refresh, kitchen relocation, bathroom rebuilds and treatment of persistent basement dampness.
Scope of work
Condition survey, controlled demolition, replumbing, rewiring, basement waterproofing, new interiors and external painting.
Challenges on this project
The basement dampness turned out to be a failed external drain rather than groundwater, which meant the problem could be solved from outside at a fraction of the cost of internal tanking.
Outcome
Basement has remained dry through two monsoons since completion.
Key materials and systems
- Crystalline waterproofing to basement walls
- CPVC replumbing throughout
- Engineered wood and vitrified flooring
- Asian Paints Apex exterior
Project summary
- Category: Renovation
- Location: Nirvana Country, Gurugram
- Built-up area: 4,100 sq.ft.
- Duration: 5 months
- Year: 2024
- Status: Completed
Planning something similar?
Send us the plot details and we will tell you what is realistic on programme and budget — including if the answer is uncomfortable.
Discuss Your Project Explore our servicesThe project